More than 100,000 workers are on site as construction advances on the 35 billion US dollar (128 billion dirham) expansion of Al Maktoum International Airport, Dubai Airports Chief Executive Paul Griffiths told reporters on Tuesday, according to Gulf News.
Griffiths said piling is starting, groundworks are well under way and major construction contracts are being discussed and awarded, so âitâs definitely a live projectâ.
He gave a budget of âsomething likeâ 35 billion dollars, Gulf News reported. He did not give an updated value for contracts awarded or say which construction packages have entered their next phase, the newspaper said.
The developer, Dubai Aviation Engineering Projects, said in June that more than 17,000 concrete piles had been installed and over 45 million cubic metres of earth had been excavated, according to Gulf News.
The developer expected the workforce to peak at about 120,000. Earlier this year, officials also outlined plans to award more than 55 billion dirhams of additional contracts in 2026 for terminal structures, concourses, and supporting infrastructure, the newspaper reported.
The latest phase of the expansion was approved on April 28, 2024, by Sheikh Mohammed bin Rashid Al Maktoum, Vice-President and Prime Minister of the UAE and Ruler of Dubai, according to Gulf News.
The airport is meant to replace Dubai International Airport (DXB) as Dubaiâs main international gateway. Its master plan provides for five runways, hundreds of aircraft stands, and a capacity for 260 million passengers and 12 million tonnes of cargo a year. The first phase is due to begin operating in 2032, with capacity expanding gradually, the report said.
Dubai International Airport handled 50.4 million passengers in the first nine months of 2026, down 28.1 percent from a year earlier, according to Dubai Airports figures reported earlier by Gulf News.