HSIAâs T3 to be fully operational by Feb 2028: Millat
āĻĒā§āϰāĻāĻžāĻļ: āϏā§āĻŽāĻŦāĻžāϰ āĨ¤ āύāĻā§āĻŽā§āĻŦāϰ ā§¨ā§Š, ⧍ā§Ļ⧍ā§Ŧ
The much-awaited Third Terminal at Hazrat Shahjalal International Airport (HSIA) could become fully operational by February 2028, with the government allowing up to 14 months to complete the transition from its planned partial opening on December 16 this year.
Civil Aviation and Tourism Minister M. Rashiduzzaman Millat announced the timeline on November 23 following a meeting at the Secretariat in Dhaka, outlining a phased operational plan for the country's flagship airport infrastructure project.
Asked how long it would take to bring the terminal into full operation, Millat said the process could require a maximum of 14 months from the initial launch. The government aims to sign a concession agreement with a Japanese consortium by November 30, paving the way for limited passenger operations from December 16, coinciding with Bangladesh's Victory Day.
According to the minister, the concession agreement covering the terminal's operation and management has already been finalised, with formal signing now the immediate priority.
Four Flights to Mark Opening
The terminal will initially handle four flights, with Biman Bangladesh Airlines operating the first flight on the opening day. The number of flights will subsequently increase as the Japanese operator gradually expands operational capacity. Discussions are also underway to introduce services to Singapore and other international destinations through the new terminal.
Millat explained that the original plan envisaged launching the facility at 25 percent of its capacity. However, the consortium would not be ready to operate at that level immediately. The government has therefore opted for a smaller initial operation, allowing the operator to progressively scale up services.
The minister noted that a phased introduction of flights is common at major international airports, where operational systems and passenger services are brought into use gradually.
A Longer Road to Full Capacity
The revised timetable makes an important distinction between the terminal's ceremonial opening and its full commercial operation. While December 16 remains the target for the first flights, the government now expects the transition to full capacity to continue through 2027 and potentially into February 2028.
The phased approach will place considerable importance on operational readiness, coordination among aviation stakeholders and the gradual introduction of passenger-handling services.
Once fully operational, the Third Terminal is expected to significantly strengthen HSIA's passenger-handling capability, modernise airport services and support Bangladesh's ambition to become a competitive regional aviation hub.